13556-015.1 L51 AND L52 PUMP STATION (P-717 AND P-718) - ODOR CONTROL (IR)

Status

Accepting Bids

Bid Date5/26/22 2:00pm

Company & Contacts

Metropolitan St Louis Sewer District

Elizabeth Goetz,egoetz@stlmsd.com  

A general description of the work to be done under these contract documents is described as follows.
•L-51 Pump Station Odor Control System Replacement:
oDemolish existing biofilter odor control system, install new activated carbon odorcontrol system and complete work as indicated in the contract documents.
•L-52 Pump Station Odor Control System Replacement:
oDemolish existing biofilter odor control system, install new activated carbon odorcontrol system and complete work as indicated in the contract documents.
oSeal gap between the concrete odor control foundation and the concrete dry wellfoundation.